Case Study

Bramley Sewer Scheme

A new foul water rising main for Thames Water — combining directional drilling and open excavation to extend network capacity at the Bramley Storm Tank with minimal surface disruption.

Aerial view of the Bramley Sewer Scheme route.

Client

Thames Water

Programme

10 weeks · Apr 2026

Rising Main

796m of 225mm PE100

Scheme Value

£1.3M

01 — Overview

A new foul rising main for the Bramley network

The Bramley Sewer Scheme delivered a new foul water rising main for Thames Water — connecting into the existing network at the Bramley Storm Tank via a new 1500mm chamber. The 10-week programme commenced on 27 April 2026 and represented a £1.3M investment in local network capacity.

The scope combined directional drilling with open excavation, along with a short gravity sewer connection, ancillary fittings and slab crossings — designed to extend network performance and resilience while minimising disruption to the surrounding residential and agricultural land.

02 — Scope of Works

Six workstreams, end to end

The 10-week programme covered six interlocking workstreams — from the rising main itself to the chamber, gravity sewer connection, ancillaries and ditch crossings.

1

1

Rising Main

~796m of 225mm OD SDR11 PE100 foul rising main installed and commissioned.

2

2

Directional Drilling

~646m of sewer installation using directional drilling, minimising surface disruption across the route.

3

3

Gravity Sewer

8m of DN375 concrete gravity sewer, connecting to the existing Thames Water manhole.

4

4

New Chamber

1500mm diameter chamber constructed and commissioned at the Bramley Storm Tank connection.

5

5

Ancillaries

One washout, two air valves and associated chambers installed along the rising main.

6

6

Ditch Crossings

Four concrete slab crossings over existing ditches along the easement.

Site Photography

On site

Easement — topsoil strip & haul route.

Aerial view — scheme route & residential context.

Chamber construction & connection works — Bramley Storm Tank.

Easement — topsoil strip & haul route.

Chamber construction & connection works — Bramley Storm Tank.

Aerial view — scheme route & residential context.

Easement — topsoil strip & haul route.

Aerial view — scheme route & residential context.

Chamber construction & connection works — Bramley Storm Tank.

03 — Outcomes

Delivered on time, on budget, to specification

796m

Of 225mm PE100 rising main installed and commissioned along the route.

646m

Delivered via directional drilling to minimise surface disruption.

£1.3M

Scheme value, delivered to specification over a 10-week programme.

Foul water rising main successfully delivered, improving network performance and resilience with minimal surface disruption to the surrounding residential and agricultural land.

Have a project in mind? Let's talk about how MAIUS can deliver it.

Contact Us

Delivering innovative civil engineering solutions that enhance infrastructure, foster growth, and build partnerships.

Address

Unit 3
St Albans Road
Gloucester
GL2 5FW

Mon–Fri 8:00 – 17:00

Copyright © 2026. All Rights Reserved.

Delivering innovative civil engineering solutions that enhance infrastructure, foster growth, and build partnerships.

Address

Unit 3
St Albans Road
Gloucester
GL2 5FW

Mon–Fri 8:00 – 17:00

Copyright © 2026. All Rights Reserved.

Delivering innovative civil engineering solutions that enhance infrastructure, foster growth, and build partnerships.

Address

Unit 3
St Albans Road
Gloucester
GL2 5FW

Mon–Fri 8:00 – 17:00

Copyright © 2026. All Rights Reserved.